Good news: Kenya has postponed its plan to build nuclear power plant to 2036

Updated power development plan prepared by the Ministry of Energy and covering the period 2017 to 2037, now show that the earliest the country can build the nuclear plant is 2036 and not 2027 as initially planned.

In the revised plan, the first unit is expected to be completed in 2036, followed by another in 2037, making it the last project in the ministry’s 20-year plan for power generation expansion.

“All energy sources were considered in the system expansion planning. However, it is noteworthy that nuclear was not brought on board in both optimised and fixed MTP cases,” reads the updated plan shared by the Ministry.

In addition to the delay, the plan size has been scaled down. Initially, Kenya was to construct two nuclear power plants, each with a capacity of 1,000 megawatts (MW) at a total cost of $4.05 billion (Sh405 billion) per plant.

Full article: Business Daily

 


 